Aecon was an integrated joint venture partner on the team responsible for carrying out the design and construction portions of the road’s final 27-kilometre northeast section, running from Manning Drive to Whitemud Drive.  

Aecon carried a 22.5 per cent interest in the project scope with partners Flatiron Constructors, Dragados, and Lafarge, operating under a Public-Private Partnership (P3) framework. The team was subcontracted to complete the work by Capital City Link General Partnership (CCLGP), a P3 consortium awarded the overall $1.81-billion contract in 2012 to design, build, operate and partially finance the Northeast Anthony Henday Drive (NEAHD) project.

CLIENT
Alberta Transportation

AWARDED CONTRACT VALUE
$1.81 billion

START DATE
2012

Northeast Anthony Henday Drive Roads

27
KM LENGTH OF ROADWAY IN NORTHEAST SECTION

47
BRIDGE STRUCTURES

500
EMPLOYEES ON-SITE AT PEAK

The completion of this project provides tremendous advantages for motorists trying to get around the city. Not only does it offer greater mobility for the community as a whole, it also impacts the economy and the overall region. Thanks to this first-rate example of a project completed under the P3 building model, an estimated 40,000 motorists will have unparalleled access into and around Edmonton.
Northeast Anthony Henday Drive Bridge

Related Project

Highway 410 Widening Cars

Highway 410 Widening

Mississauga and Brampton, Ontario
The major reconstruction of Highway 410 has provided much-needed relief to the region’s ever-growing population and improved traffic flow and safety.
View Project